Supplier submitted

1650sqm ISO8 Aerospace manufacturing cleanroom facility

GKN maintained full production within its existing footprint throughout the phased redevelopment. The completed facility provided a modern, functional manufacturing environment, with increased ceiling height across 60% of the previous floor area to support future requirements. GKN praised Guardtech’s flexibility, communication and on-site support in delivering a successful project.

Supplier submitted
Aerospace
Published 16 November 2026
GKN Phase 2 3 bigger - Guardtech Cleanrooms
The challenge

GKN Aerospace needed to replace an existing cleanroom to increase manufacturing capacity, improve compliance and accommodate new projects. The installation had to fit within an ageing shipyard building, overcoming uneven steelwork, restricted service routes and weather-related water ingress. Maintaining production throughout the redevelopment was essential.

The solution

Guardtech’s Cleanroom Solutions team delivered a bespoke 1,650m² ISO Class 8 facility in two phases. A temporary dividing wall allowed production to continue while installation progressed, with 90% of its panels subsequently repurposed. Engineered 12-metre steel trusses supported a walk-on ceiling without additional internal columns, preserving valuable process space. Integrated HVAC, HEPA filtration, lighting and environmental monitoring supported the required operating conditions.

The outcome

GKN maintained full production within its existing footprint throughout the phased redevelopment. The completed facility provided a modern, functional manufacturing environment, with increased ceiling height across 60% of the previous floor area to support future requirements. GKN praised Guardtech’s flexibility, communication and on-site support in delivering a successful project.

From the project

Published with the express consent of both parties. All quotes are unedited extracts from verified reviews.